The bend is plugged on the round pipe and secured with a 50 mm wide adhesive tape.
The sleeves are secured the same way.
The image shows the fully installed vent pipe in the platform.
A telescopic channel is installed in the outer wall with automatic sealing hatch.
A connecting piece is plugged into the pipe end of the vertical venting pipe and secured with adhesive tape.
The flexible pipe made of aluminium is inserted into the connecting branch of the wall mount and secured with a galvanized pipe clamp (strap).
The other side of the flexible pipe is pushed into the connecting sleeve and secured the same way.
The plastic ventilation pipe that comes out of the floor (see Figure 4) is cut to the fitting length. A connecting piece is inserted into the pipe end and secured with adhesive tape.
The flexible Aluminium pipe of the laundry dryer is inserted into the connecting piece and secured with a galvanized pipe clamp (strap).